1 JLab Perspective on Hall A Rolf EntRequest: news of the lab with a perspective on Hall A. plans for sustainable multi-hall operations of CEBAF and prospects for full energy capability I assume Arne will cover, but I will add some perspective on scheduling recent progress in the JLEIC project and perspectives for realization. Rolf Ent Note: I took many slides from Mont/Bob … but gave it my own spin by adding some Hall A Collaboration Meeting Jefferson Lab - January 18, 2017
2 ERR (Experiment Readiness Review) in a NutshellIf your experiment includes one-of-a-kind equipment with potential novel safety implications (examples are SC magnets, tritium or high-power cryogenic targets) it requires a first-phase ERR for this equipment at the design stage. If your experiment requires items in the category above and/or equipment beyond the declared base equipment (examples are new detector technologies, new beam lines, new spectrometers), it requires a second-phase ERR before scheduling can be requested. Always check if you need a second-phase ERR well in advance of considering a request for scheduling. If your experiment only includes base equipment (as declared by the Deputy AD) and only in operation modes already executed, or only additional equipment that is a direct clone of base equipment, it only needs a third-phase ERR. 2
3 12 GeV Readiness Reviews Experimental Hall Project Date DSolenoid Cool down 11/6/2012 Solenoid Power up 1/9/2013 Tagger Magnet 12/3/2013 Cryo Target 5/8/2014 GlueX 7/1-2/2014 C Q1 Power up 1/21/2015 HB Power up 3/25/2015 Solenoid Operation 7/14/2015 B Torus Cool down (2 reviews) 4/13/2016 6/27/2016 Torus Power up 7/18/2016 L3 trigger* 7/22/2016 SHMS Detectors 8/24-25/2016 Q2/Q3/D Magnets 10/12/2016 * Not really 12 GeV Equipment transitioning, but closely related to the 12 GeV design for GlueX/hall D 3
4 Experiment Readiness ReviewsExperimental Hall Experiment Date A Hall A restart 12/9/2013 B HPS 7/10/2014 DVCS/GMp 9/18/2014 Accelerator Bubble Chamber Experiment 8/18/2015 Tritium Target Review 9/15/2015 PRad Experiment PRad Experiment 2nd Review 11/12/2015* 3/25/2016 LERF DarkLight 12/7/2015 Series of (4) Tritium Experiments 3/16/2016 APEX 4/7/2016 PREX-CREX 6/1-2/2016* CLAS12 Ancillary Equipment 6/13-14/2016 D Primakoff Experiment 7/20/2016* 40Ar Spectral Function 7/21/2016 C Series of (7) Initial Experiments 8/24-25/2016 Pre-ops and first commissioning exp. 12/6-7/2016 + successful accelerator readiness review phase 4 (B & C) on January , 2017 * Did not pass the Experiment Readiness Review 4
5 Enhancements beyond 12-GeV Upgrade• Hall A DVCS Calorimeter (France - Orsay) installed/used/de-installed • Hall A SBS – WBS1 complete, WBS2 & 3 near-complete (Capital Equipment (CE)) • Hall A SBS GEMs (Italy INFN, UK), Hadron Cal. (CMU+INFN) ongoing (ops) • Hall A pre-R&D toward PV (MOLLER magnet concept, with MIT) ongoing (ops) • Hall A SOLID (China, Temple, Duke, ANL, …) ongoing (magnet - CE) • Hall A APEX septum magnet (Canada, Stony Brook) complete • Hall B longitudinally polarized target (ODU …, NSF/MRI) ongoing (infrastr. - CE) • Hall B forward tagger (Italy INFN & NSF/MRI) complete • Hall B RICH sector(s) (Italy INFN, Chile) near-complete (PMTs, materials - CE) • Hall B MicroMegas (France - Saclay) near-complete • Hall B Central Neutron Detector (France - Orsay) complete • Hall B Heavy Photon Search (HPS) (DOE HEP, France, INFN) complete/in use • Hall B H Gas Target for Proton Charge Radius (NSF/MRI) used/de-installed • Hall C Kaon Detection System (CUA …, NSF/MRI) installed • Hall B,C Backward nucleon detection system (Israel/ODU/MIT) ongoing • Hall C Neutral-Particle Spectrometer (CUA …/France/UK/Armenia, NSF/MRI) ongoing • Hall D DIRC-based PID/Cherenkov system (JLab/IU/MIT) ongoing (CE) • Hall D Discussions with China on calorimeter upgrades planning + CE • LERF: DarkLight Phase-I Equipment (MIT …, NSF/MRI) ongoing, test completed • Injector: Bubble Chamber for 16O(g,a)12C inverse kinematics (ANL) ongoing
6 SBS Construction Nearing CompletionProject started Oct 2012 – to be completed Feb 1, 2017 3 major WBS elements and 5 dependencies: (HCAL (CMU), GEM trackers (INFN), Polarized 3He (UVa&JLab), GRINCH (W&M), ECAL (SBU&JLab)) Successful 4th annual review Nov 2016 Project on track for completion, transition to operations plan likely includes tracking of dependencies GEM production near-final at UVa: 39/40 complete (Dec 2016) Status February 2015: 6/40 All GEM electronics finalized, production at INFN, QA at UVa Led by Idaho State U including sci. fiber polishing & assembly CDET plane assembly and testing led by CNU Two planes, each 3 modules, completed Aug 2016 All scope on site, to be visually verified by engineers RE updated slide (2/3/2016 ); AL formatting edits 06Feb WBS1 Completed 01/22/16 WBS3 GEMs & Electronics WBS2 Coordinate Detector
7 Future Projects MOLLER experiment (Possible MIE – FY17-20)– Standard Model Test – DOE science review (September 2014) – strong endorsement – Director’s review held December 15-16, 2016 Technical, cost & schedule Report due in mid January – Still hope for FY18 start SoLID – CLEO Solenoid – Chinese collaboration – Director’s review (Feb. 2015) new pre-CDR almost complete – Collaboration briefing to DOE-NP (Nov. 2015)
8 FY17 Budget Nominally, first year of full operations in 12 GeV-era and Operations budget should have increased correspondingly. President’s Budget (NP = $636M) up 3% JLab Ops up $5.5M; but insufficient for full operation Major increases in isotope program (+$8M) and RHIC (+$7.5M) Senate Mark: $636M Language for FRIB construction and RHIC ops House Mark: $620M Language for FRIB construction, RHIC ops, and CEBAF ops No Federal Budget yet: Continuing Resolution (CR) until April 28. Held to FY16 level - NP $15.4M below Pres. Budget JLab $5.5M below Pres. Budget NP=DOE Office of Nuclear Physics
9 FY17 Planning Anticipate considerable uncertainty in transition between Administrations NP additional Ops support? If a full year CR, NP has substantial shortfall FY16 CR Budget level: Major impact on non-labor spending (travel, hardware, contract labor, etc.) Reduced Weeks of Accelerator Operation: Pres Budget = 23 weeks FY16 Level = 16 weeks Workforce: New/replacement hires limited to critical needs In extremis, forced vacations and furloughs would be considered Reduction in force not anticipated U.S. has made a major investment in CEBAF. Laboratory has a clear mission, nuclear physics and accelerator technology, which is supported by DOE. We will work to mitigate negative effects of budget constraints on all aspects of the program, especially the workforce.
10 CEBAF Three-Year ScheduleHall A Hall D Accelerator Hall B Hall C Activity Beam Fiscal Year 2016 2017 2018 Calendar Year CLAS12 Construction/Installation Physics SHMS Construction/Installation CEBAF Three-Year Schedule Feb 2016 Non-CLAS12 Ops* SBS Construction Comm. Opportunistic Nov 2016 Modified Nov. 2016 * PRad Summer 2016 run Beam for Commissioning Beam for Physics Non-CLAS12 Ops JLab User Satellite APS Meeting January 10
11 12 GeV Approved Experiments by PAC Daysxx 28 “A Decade of Experiments” – could be 6 or 15+ pending budgets etc.
12 Priorities Folded into Scheduling12 GeV Project Priorities Scientific Priorities – High Impact and/or Timeliness Funding Agency Commitments such as DOE/NP Capital Equipment Commitments (SBS, BRICH, DDIRC, etc.) DOE/HEP Commitment (HPS) NSF/MRI Funded Equipment (e.g., PRad, Hall C SHMS Detectors, NPS) International Funded Equipment (e.g., BRICH) Pragmatic Reasons such as Safety Issues – ALARA (like use HRS not BigBite with Tritium target experiments, Tritium only one year on site) Scientific Priorities – Science Rating or Verify Operational Requirements (like new beam requirements, new detector commissioning, etc.) What is ready and “fits” into schedule Installation times required Likelihood to get science results out fast Impact on Young Scientists and/or PhD Students Can only run 3 out of 4 Halls together (up to Fall 2018?) What could run beyond May 6 Power Meter Readout
13 Operations Constraints – some examplesHalls B and C are gearing up for 12-GeV pre-ops KPP demonstration they must get priority in accelerator operations. We can run with a Hall multiplicity of 3.0 only, out of 4 Halls, until Accelerator Operations has fully commissioned potential 4-Hall Beam Delivery (Fall 2018) BUT, to get to a Hall multiplicity of 3.0 with a versatile and reliable machine will take some effort see Arne’s talk In Hall A, we plan to bring the closed 3H target cell on site for a full-year series of experiments on 3H. The plan is to return the 3H after one year to Sandia. This restricted duration puts pressure on the series of 3H experiments scheduled (they require 74 PAC days – exactly 23 weeks), especially with a long CR Had to delay as we could only do a limited run this Spring Hall compatibility. E.g., the precision longitudinal-transverse separated cross section science program in Hall C often requires periods of changed linac energy settings, sometimes but not always compatible with the programs in other Halls not a direct issue for 2017 given the schedule change, but relevant for 2018 + Cryogenics, polarization constraints, labor availability, facilities improvements, etc. 13
14 2015 NSAC Long Range Plan RECOMMENDATION I The progress achieved under the guidance of the 2007 Long Range Plan has reinforced U.S. world leadership in nuclear science. The highest priority in this 2015 Plan is to capitalize on the investments made. Operate 12 GeV CEBAF RECOMMENDATION II We recommend the timely development and deployment of a U.S.-led ton-scale neutrinoless double beta decay experiment. RECOMMENDATION III We recommend a high-energy high-luminosity polarized EIC as the highest priority for new facility construction following the completion of FRIB. Jefferson Lab EIC (JLEIC) development RECOMMENDATION IV We recommend increasing investment in small-scale and mid- scale projects and initiatives that enable forefront research at universities and laboratories. MOLLER, SoLID
15 EIC Developments EIC User meeting at ANL July 7-10, 2016UG charter, elections (IB chair – Christine Aidala) 2017 EIC UG Meeting in Trieste, Italy DOE-NP will increase EIC accel. R&D in FY17 – Through ‘tax’ on JLab/BNL – Peer review held for November 29-December 2 - report to be released in mid January National Academies Study, Chair Gordon Baym, University of Illinois, Urbana Champaign, first meeting projected for January 2017.
16 Integration IR: JLEIC total acceptance detectorPossible to get ~100% acceptance for the whole event Scattered electron Particles Associated with Initial Ion Particles associated with struck parton Relatively large crossing angle (50 mr) combined with large aperture final focus magnets, and forward dipoles are keys to this design.
17 Bunched Ion Beam Cooling – preliminary resultsA collaboration of JLAB and Institute of Modern Physics (IMP), China The 1st experiment was carried out on May 17-22, 2016, at Lanzhou, China A 7MeV/u 12C6+ ion beam stored in the IMP CSRm ring, either coasting or captured by 450kHz RF system (two long bunches) Cooling of both coasting and bunched ion by a pulsed electron beam are observed: first successful step of experimental demonstration of bunched beam cooling Data analysis both at IMP and JLAB is in progress Initial 1D modeling with RF capture and bunching shows the ion cooling and synchrotron sideband effects, agree with experimental observations Experiment data observation on BPMs cooled ion bunches uncooled ion bunches Electron bunches 1.5ms
18 JLEIC energy reach and luminosityJust implemented a baseline modification (essentially: add strong cooling back in and optimize collider parameters, but no change of concept) Baseline = 3T Note: Baseline choice is a mix of risk, total detection capabilities, energy/luminosity needs. Baseline gives access to start all science of EIC white paper.
19 JLEIC possible timeline (eRHIC similar)Activity Name 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 12 GeV Operations 12 GeV Upgrade FRIB EIC Physics Case NSAC LRP NAS Study CD0 EIC Design, R&D Pre-CDR, CDR CD1(Down-select) CD2/CD3 EIC Construction pre-project on-project Pre-CDR CDR CD0 = DOE “Mission Need” statement; CD1 = design choice and site selection CD2/CD3 = establish project baseline cost and schedule update: 1/13/17
20 Director’s PerspectiveEmphases Core Nuclear Physics Finish the upgrade project, safely, on time, and within budget. Full-time operations. Operations budgets continue to be a concern here. Reliability and Risk Mitigation Advance new NP projects beyond the upgrade Develop Jefferson Lab EIC design: Technical Designs, Collaboration, (Land now secured) Technology Collaborations Large projects, like FRIB and LCLS-II, within context of a Nuclear Physics program – management is key Management/Personnel Operations Functions: Facilities, Procurement, Financial Management, Budget Office, Human Resources, Information Technology, Legal, ES&H are vital to the functioning of the lab What the lab can achieve depends on your efforts, Jefferson Lab successes will be your successes. Jefferson Lab world- leading Nuclear Physics
21 Jefferson Lab 2025 Campus PlanWe appreciate your support of the multiple traffic pattern changes. We see the Hogan Road changes as a definite improvement to our access.