S&P Electrical Workshop 2016

1 Standards & Preferences Electrical Workshop- Section IX...
Author: Annabelle Nash
0 downloads 1 Views

1 Standards & Preferences Electrical Workshop- Section IX July 14th, 2016

2 S&P Electrical Workshop 2016Agenda Welcome Introductions Purpose of Workshop EEM Organizational Structure S&P Section IX Layout Review of Updates Reoccurring Themes Q&A

3 S&P Electrical Workshop 2016Electrical & Energy Management (EEM) Organizational Structure Rick Raike - Chief of Electrical and Energy Management

4 Electrical and Energy Management – Organizational Chart FY-16July 2015

5 S&P Electrical Workshop 2016S&P Section IX Layout Format change from table format to specification format Consist of two sections – Pump stations and Treatment Plants Pump Stations consist of 30 items and Treatment Plants consist of 36 items Attachments A~E Grey highlights will indicate latest changes

6 S&P Electrical Workshop 2016Pump Station Item# Item Description Page# 1 Switchgear and MCC 3 2 Emergency Generators 7 Energy Efficient Motors 13 4 Sump Pumps 14 5 Level Sensing Systems 6 Variable Frequency Drives (VFDs) 15 Watt Hour Meter (for MCCs or individual motors) 17 8 PLCs 9 Exhaust Fans 10 Lighting 18 11 Concrete Housekeeping Pads 20 12 Conduit and Conduit Systems Wire 22 Relays 23 Lockout/Tagout  Safety 16 Switches/Receptacles/Plugs Electric Heaters 24 Electrical Drawings 19 Safety Switches (fused or unfused) Transformers 25 21 Metering Vaults/Pits Pressure Sustaining/Regulating Valves Alarm Systems 26 Flow Meters 27 RTUs Louvers/Dampers Cathodic Protection 28 Junction Boxes and Misc. Enclosures 29 Panel Boards/Control Panels 30 Miscellaneous Electrical Item # Treatment Plant Page# 1 Switchgear 30 2 MCCs 33 3 Emergency Generators 37 4 Energy Efficient Motors 43 5 Sump Pumps 6 Level Sensing Systems 7 Variable Frequency Drives (VFDs) 46 8 Metering Packages for Switchgear, MCCs or Individual Motors 47 9 PLCs_TP 10 Exhaust Fans 48 11 Lighting 12 Concrete Housekeeping Pads 50 13 Conduit and Conduit Systems 14 Wire 53 15 Relays 55 16 Lockout/Tagout  Safety 17 Switches/Receptacles/Plugs 18 Heaters 56 19 Electrical Drawings 20 Safety Switches (fused or unfused) 21 Transformers 57 22 Metering Vaults/Pits 23 Pressure Sustaining/Regulating Valves 58 24 Flow Meters 59 25 RTUs 60 26 Louvers/Dampers 27 Transfer Switches 28 On-Line Vibration Monitors 61 29 Panel Meters Analyzers/Monitors 62 31 Miscellaneous Instrumentation 64 32 Miscellaneous Electrical 65 Heating and Cooling 34 Junction/Pull Boxes and Miscellaneous Enclosures 66 35 Panel Boards/Control Panels 36 Distributive Control System (DCS) 67

7 Table Format- S&P Electrical Workshop 2016PUMP STATION Electrical and Instrumentation Requirements Electrical Equipment/Item Manufacturer Specific Criteria Day Tanks Pryco Tramont - UL Listed – double wall - Provide with Oberndorfer bronze gear type pump. Pumps with rubber or nitrile impellers will not be accepted - Provide with a low level alarm and light - Size for 2 hour minimum running time - Provide a fuel level indicator on the day tank - Provide a 2 pump system. Each pump shall be capable of pumping 100% fuel oil throughout the entire system. - Provide “Not in Auto” lamp or other warning device - Use momentary switch for tank fill/test

8 Specification format- S&P Electrical Workshop 2016Day Tanks Manufacturers Pryco Tramont Specific Criteria UL Listed – double wall Provide with Oberndorfer bronze gear type pump. All pumps must be mounted on Day Tank. Pumps with rubber or nitrile impellers will not be accepted Provide with a low level alarm and light Size for 2 hour minimum running time Provide a fuel level indicator on the day tank Provide a 2 pump system. Each pump shall be capable of pumping 100% fuel oil throughout the entire system. Provide “Not in Auto” lamp or other warning device Use momentary switch for tank fill/test

9 Day Tank - S&P Electrical Workshop 2016All pumps must be mounted on the Day Tanks. In ground pumps not preferred, but may used in site specific applications. See pg. IX-11

10 S&P Electrical Workshop 2016E- Stops -Mfr: Pilla -Model: GS120 See pg. IX-40

11 S&P Electrical Workshop 2016Review of Updates (Part 1)

12 Generator Section - S&P Electrical Workshop 2016Review of Updates (Part 1) Generator Section for Pump Stations and Treatment Plants. Size air, fuel, and oil filters to provide a minimum 250 hours before servicing (a minimum of 100 hours was previously stated). See pg. IX-9 & 41 Removed - Mfr. American Battery Charger. See pg. IX-10 & 42 Added - SENS Battery Charger. See pg. IX-10 & 42

13 Generator Section - S&P Electrical Workshop 20164. Added - Size radiator to prevent overheating in the most severe conditions; changed from 110°F to 122°F. See pg. IX-41 5. Added - 4D starting batteries are not acceptable (Use 8D only). See pg. IX-11 & 42

14 S&P Electrical Workshop 2016Variable Frequency Drives (VFD’s) 1. Change the name from Power Logix to Power Flex Series (Allen Bradley) See pg. IX-16 & 49

15 S&P Electrical Workshop 2016Rubber Matting What is considered OSHA approved matting? Electrical rated matting that meets the Type II ASTM D178 Standard. See pg. IX-10, 35, & 39

16 S&P Electrical Workshop 2016Conduits Painted red in pump station per request of the owner (Does not apply for PVC Coated Rigid). Refer to Section X Coatings manual page 148. See pg. IX-21

17 S&P Electrical Workshop 2016MCC/Switchgear Fasteners Provide extra fasteners when ordering gear (spare parts). See pg. IX-33 and IX-36

18 S&P Electrical Workshop 2016Analyzers/Monitors Added E&H probe for Incinerator scrubber water (process pH); Specific applications at Treatment Plants See pg. IX-67

19 S&P Electrical Workshop 2016Level Sensing Systems Bubbler Remove Bell & Gossett as Mfr. Add model 3HBB-10-M300 AX (Dual Head Air Compressor) or equal See pg. IX-15 3. Separate circuit for each compressor (Panel schedule)

20 S&P Electrical Workshop 2016Voltage Test Points Mfr. Safeside See pg. IX-7 and IX-39

21 S&P Electrical Workshop 2016DIN Rail Add Panduit Panduct DIN Rail Wiring Duct See pg. IX-5

22 S&P Electrical Workshop 2016Review of Updates (Part 2)

23 S&P Electrical Workshop 2016Review of Updates (Part 2) Pump Station section 16- provide one weatherproof (WP/Watertight) receptacle with lockable cover on the exterior wall of the pump station on a separate circuit; separately switched -> must not be hot at all times. See pg. IX-25 Provide high level float ball for alarms See pg. IX-15 Provide Intrinsically safe barriers See pg. IX-16

24 S&P Electrical Workshop 2016Add Remote Switch Operator to open/close main circuit breaker outside of the arc flash boundary. See pg. IX-32

25 S&P Electrical Workshop 2016Add ARMS “Arms Reduction Maintenance Switch or Equal; When activated downstream incident energy levels will be reduced. See pg. IX-32

26 S&P Electrical Workshop 2016Add LSI or LSIG (>=1000A) Electronic Trip Units See pg. IX-33

27 S&P Electrical Workshop 2016Add Short Circuit, Coordination, and Arc Flash requirements to specifications (Arc Flash calculations must be performed for both Utility bus and Generator bus); A label must be added to the generator breaker. See pg. IX-31

28 S&P Electrical Workshop 2016Push-buttons, selector switches, etc. must be NEMA rated only (Some Mfr. Have both NEMA/IEC ratings on components). See pg. IX-34 & 37

29 S&P Electrical Workshop 2016ETM Add Mfr. Crompton and ENB Elapsed Time Meters; Yokogawa UL certification in question. See pg. IX-65

30 S&P Electrical Workshop 2016Surge Protection Devices Remove SPD Type IC4/IC6 Surge Protectors Don’t use DC powered surge protection on field devices (4~20mA). Don’t use AC powered surge protection for field devices. All SPD should be installed at the incoming power section of the gear.

31 S&P Electrical Workshop 2016Splicing No splicing allowed on HRSD projects without approval from Engineer/Owner. No splicing in man-holes If granted approval, splicing must be perform by certified splicer. May require above ground installation.

32 S&P Electrical Workshop 2016Variable Frequency Drives- New circuit diagram

33 S&P Electrical Workshop 2016Tegam Windows J. Matt Ferguson  DRISCOLL AUTOMATIC  918/ – Main  918/ – Fax  918/ – Cell  P.O. Box  52583  Tulsa, OK 74152

34 S&P Electrical Workshop 2016Tegam Windows- AW1012 Can be eliminated if installed in condition spaced. 

35 S&P Electrical Workshop 2016Conduit schedule vs. Circuit Method Some consultants method of design does not use conduit schedules so individual conduit tag numbers do not exist.  The one line diagrams use circuit numbers. For power circuits (except for lighting and receptacles circuits) a conduit is dedicated to that circuit.  For control and instrumentation circuits; They often have multiple circuits in a common conduit.

36 S&P Electrical Workshop 2016Labeling Method (phenolic labels) – White lettering on Black background. See pg. IX-30, 33, & 36

37 S&P Electrical Workshop 2016Actuators EIM actuators- verify use of proper voltage 120 vs. 480V -Use proper control boards based upon required voltage.

38 S&P Electrical Workshop 2016Polaris Style Connectors not preferred ; T leads to motor (rarely used); Prefer lugs

39 S&P Electrical Workshop 2016Pump Station ATS Push to test function; manually initiate 2 hour test to start generator and assume load. After two hours the system automatically returns to utility source if available. Note: This is not an exercise function. Remove Mfrs. Cummins and SQD; Specify Eaton or ASCO. See pg. IX-11

40 S&P Electrical Workshop 2016Locate HOA switch at drives for variable speed applications Locate HOA switch at pump for constant speed applications.

41 S&P Electrical Workshop 2016Reoccurring Themes

42 S&P Electrical Workshop 2016Load Bank Test Boxes Fabrication –UL Shop Harper Sheet Metal Richmond VA (804)

43 S&P Electrical Workshop 2016Reoccurring Themes Load bank test boxes – Eaton and other Mfrs. have similar connection boxes; However HRSD standardized the use of Leviton Connectors, due to Operation’s wire spool trailers having Leviton mating connectors. Other products utilize Hubbell connectors. The Mfrs. would like for HRSD to use Hubbell connectors to prevent the modification of their UL listing.

44 S&P Electrical Workshop 2016Shop Drawing Submittal/Approval Process HRSD Electrical Staff would desire access to a file storage area, to review submittals in parallel with consultants, in an effort to streamline the overall process. Secure As-Builts/ Record Drawings before closeout of Project. Functionals and P&ID’s Interposing Relays DCU Power Supplies/Isolation transformer Arc Flash Mitigation (> 40 cal/cm2)– Design, SC, Coordination, AF analysis, and labeling.

45 S&P Electrical Workshop 2016Arc Flash – Breaker/Relay settings for contractors. Variable Frequency Drives (VFD’s) Long term maintenance plan at substantial completion. Rice Rule MOPO Generator/paralleling gear (block load or soft load)

46 S&P Electrical Workshop 2016100 ms closed transition test and 225 ms breaker timing test NFPA 820 Energy Conservation

47 S&P Electrical Workshop 2016Dominion Virginia Power Interconnection Agreement

48 S&P Electrical Workshop 2016New Electrical Services Site Plan Load Letter Power Riser Sequence of Operation Access Facility Charges – Right size equipment

49 S&P Electrical Workshop 2016

50 S&P Electrical Workshop 2016

51 S&P Electrical Workshop 2016Lighting Quick strike preferred for metal halide See pg. IX-20 and IX-52 LED preferred

52 S&P Electrical Workshop 2016Wire Stranded wire only (No solid wire allowed). Sometimes solid wire for smaller No. gauge wire will be specified. See pg. IX-23 and IX-57

53 S&P Electrical Workshop 2016Some other beneficial practices: Separate Electrical Meetings Checklist for QA/QC Involve HRSD with Electrical Inspections Verify loop checks

54 S&P Electrical Workshop 2016Turnover file, cables, hardware, and software to HRSD. HRSD needs ownership to any processor based controls and/or equipment. No proprietary programs that would not grant HRSD access to modify and/or troubleshoot.

55 S&P Electrical Workshop 2016Scheduling of Training for Equipment or New systems. Generator load bank test must witnessed by HRSD EEM and Automotive Representative. Excavation around live energized lines. Hand dig or pot hole to locate potential utility conflicts.